Generator load bank testing is an important aspect of preventative maintenance — one that requires a full assessment and examinati7on of the components of your generator under loaded conditions. When there's no recurring power outage in your area, your standby and emergency power systems only run to little or no loads for an extended period of time.
However, this is not sufficient as there's no guarantee that your generator will measure up to its full performance capacity when power failure kicks in. Generators become desensitized overtime — and at worst-case scenario if not maintained — can cause fire and safety hazards, high operating costs, and increased emissions.
Look at generator load bank testing as a surety for contingency options during emergency power situations. Despite constant exposure to light loads, your generator will need periodic testing to ensure that it meets some of the most stringent electrical codes. To eradicate unnecessary downtime and insure continuity of electricity flow, your generator should be subjected to load bank testing.
In fact, NFPA 110: Standby and Emergency Power Systems mandates that upon initial installation, acceptance testing should be conducted. Per 7.13.4.3, your standby and emergency power systems should be tested with a two-hour full load on-site in its initial commissioning.
Aside from this initial acceptance testing, monthly load bank testing is required under 8.4.1 of NFPA 110. Mission-critical infrastructures induce further proactive and preventive measures by subjecting generators to quarterly, semi-annual and annual load bank testing.
Here's the general rule of thumb: when your generator has no exposure for more than 30% of its rated kW load, that's when you need to consider load bank testing.
Under the specific clause of NFPA 110 8.4.2, generators should be imposed to a minimum load of 30% of nameplate kW rating or as recommended sufficient by manufacturer for exhaust temperature. Otherwise, neglecting scheduled maintenance or running your generator on zero to light loads can have undesirable repercussions.
Wet Stacking
Case in point, diesel generators not subjected to the minimum 30% nameplate kW rating are susceptible to wet stacking.
Operated only on light-loading or zero frequency basis, diesel generators over time accumulate carbon deposits in its specific components such as injectors, exhaust valves and exhaust system — leading to unburned fuel, dirt build-up, oil leak and black combustion gases.
To rectify this condition and burn off the carbon deposits, prime the diesel generator for load bank testing and run the engine for a few hours under 30-40% of rated load as per NFPA 110 8.4.2.
Running the diesel generator at full power will recalibrate it back to its nominal operating temperature and pressure level, clearly serving the purpose of why load bank testing should be conducted on a regular basis.
How Generator Load Bank Testing Works
Routine exercise for your electrical equipment is mandatory for its proper maintenance and efficient operational status. To test if your generator is in proper working condition, run it under artificial loads at its maximum operating capacity for a sustained amount of time.
Load banks test your generator at full kW output rating in incremental steps to verify if it can produce the highest horsepower required when wired into the generator's AC output. This load-step switching can be calibrated through a control panel to appropriately match the rated capacity of the generator.
Each time you place an additional kW load by, critical data such as engine parameters — adequate operating temperature and pressure level — are recorded simultaneously to gauge the efficiency of your generator. Aside from load bank testing, you can also utilize infrared scanning under preventive measures for early detection of problems.
Specifying load banks involves factoring in physical configuration and installation considerations. Load banks can either vary as permanent or temporary, covering full range of uses — unit-mounted, radiator-mounted or portable. When installing load banks, location is the primary issue to be considered.
For permanent load bank installation, minimum physical separation between load banks, building and landscaping is required for proper cooling airflow and damage control. Same principles of appropriate site location also apply for the tap box of portable load banks.
Conclusion
As the demand for reliable emergency power system upsurges, so does the generator load bank. Investing in periodic load bank testing for your generator assures that you have a myriad of benefits inclusive of backup capability, proactive problem detection, optimal cooling system performance and wet-stacking elimination.
Our expert electrical engineers will guide you through the design specifications so you can reap the all-in-one perks of generator load bank testing.